Ford has shipped the first lithium iron phosphate battery cells from its Michigan plant to Louisville, Kentucky, where they will power prototypes of the Fathom, the $28,350 electric pickup it plans to launch next year, the company said on Wednesday.
“The first lithium iron phosphate (LFP) prismatic battery cells are rolling off the line at BlueOval Battery Park Michigan and headed to Louisville Assembly Plant to power Ford Fathom prototypes,” Charles Poon, Vice President of Hardware Engineering, wrote in a company post.
“With this milestone, Ford is now in the battery business and will be the first to deliver LFP batteries in the U.S. for mainstream consumer automotive use,” he wrote.
“Ford is officially in the battery business,” Chief Executive Officer Jim Farley wrote on X on Wednesday. “We’ll be the first to deliver LFP batteries in the U.S. for mainstream consumer automotive use and I couldn’t be prouder of the Ford team.”
“This is a significant step for us,” he added. “We’re building capability to deliver batteries for more affordable electric vehicles and applying that same LFP technology and manufacturing expertise to build a new energy storage business with Ford Energy.”
The cells are made in Marshall, Michigan, with technology licensed from China’s CATL, an arrangement that has drawn criticism from the Trump administration.
Cell production at the $3 billion plant started in October, Ford told reporters. The company did not say how many cells it has shipped, or disclose the Fathom’s battery capacity or range.
Ford’s claim to be first rests on the words “mainstream consumer automotive use.” Tesla shipped its first Megapacks built with its own Nevada-made LFP cells in the third quarter, but those go into energy storage.
Rival General Motors is converting lines at its Spring Hill, Tennessee, cell plant to LFP with partner LG Energy Solution, with full commercial production targeted for late 2027, GM said in July 2025.
In the meantime it imports battery packs from China for the Chevrolet Bolt.
More on Ford
- Ford CEO Says New Midsize Pickup Will Go Into China’s Price Point Next YearOctober 30
- Ford’s Fathom EV Truck Castings Pass 5,000 Ahead of 2027 LaunchOctober 28
- Ford’s Fathom Nears Pre-Orders as Farley Warns of ‘a Heck of an Effort’October 1
- Bank of America Cuts Nio, XPeng and Lucid, Adds Tesla, Rivian and FordNovember 16
From First Cells to First Shipment
The shipment comes five months after Ford said workers had assembled the plant’s first complete cells.
“Team members now assemble our first full LFP prismatic cells from slurry to coating and formation,” Scott Davis of BlueOval Battery Park Michigan wrote in a June 17 post, adding that the plant was “on track to ship electric vehicle batteries in 2026.”
More than 500 employees had joined by then, with a plan to reach 800 by the end of the year and a goal of 1,700 jobs, Davis said.
“The shipment caps years of work by the team that designed, built, and launched the plant on schedule,” Poon wrote on Wednesday. “Ford now delivers cells at a plant it owns and operates.”
Poon’s post refers both to cells headed to Louisville and to “the battery packs on their way” there, without saying where those packs are assembled. “Next, we plan to have the battery pack plant up and running in Marshall in 2027 ahead of launch,” he wrote.
Ford is still in the early stages of certifying its processes and plans to ramp up cell production next year, it told reporters.
Ford announced the Marshall plant in February 2023 as a $3.5 billion project with 2,500 jobs and about 35 gigawatt-hours of annual capacity, calling it “the country’s first automaker-backed LFP battery plant.”
It cut the plan later that year to about 20 gigawatt-hours and 1,700 jobs. The company said in August 2025 it was spending about $3 billion there and nearly $2 billion to retool Louisville.
Michigan’s Strategic Fund reduced the state incentives for the plant in July 2024 from more than $1 billion to between $384 million and $409 million.
40 Cells a Minute
The plant’s assembly lines “can deliver 40 cells every minute, making it among the fastest LFP prismatic battery assembly lines outside of China,” Poon wrote. Ford bases that comparison on cells per minute, according to a footnote.
“That pace helps drive down battery costs, and the facility has capacity for more,” he added.
Workers use AI-powered image recognition to spot defects during production. “Our goal is to make defective cells so rare that we track their frequency per billion cells rather than per million,” Poon wrote.
Why Ford Chose CATL
Poon traced the choice of chemistry to Alan Clarke, Vice President of Advanced Development Projects, who challenged the team behind Ford’s Universal EV Platform to “find an efficient LFP prismatic battery” to make electric vehicles more affordable.
“We wanted a technology that was proven in the field, ready to manufacture at scale, and suited to what we were building,” Poon wrote. “That led us to the world’s leading battery manufacturer, CATL, whose batteries power 30 million vehicles across the globe.”
LFP chemistry “uses no nickel or cobalt, which helps hold down costs,” he wrote, and the Fathom’s pack serves as part of the vehicle’s structure. “We chose prismatic, or rectangular, cells because they fit directly into the chassis and cut structural costs.”
The license has been a political target. Transportation Secretary Sean Duffy wrote to Ford in September that his department “remains deeply alarmed” by its reliance on CATL technology at Marshall, in a letter Ford called “a wrongheaded attempt to capture headlines.”
CATL has been on the Pentagon’s list of Chinese military companies since January 2025.
Ford described the CATL deal at the time as “a limited technology-licensing and services agreement, not a joint venture or foreign-owned manufacturing operation.”
“It’s our factory, our people in Marshall, Michigan. But it’s their IP,” Farley said on September 29. “It’s better than importing batteries.”
“If we want to get to being able to produce affordable EVs in the United States, we need to also do it the fastest way possible,” Clarke told reporters during a tour of the plant on Tuesday. “CATL being the biggest in the world means that they’re the best supplier to get us that technology and help us learn ourselves how to produce LFP cells.”
The license also bears on federal tax credits. John Moolenaar, the Michigan Republican who chairs the House Select Committee on China, asked Farley in a January 27 letter whether “any amendments, expansions, or new scopes of work” had been added to the arrangement since July 4, 2025, and whether Ford intends to claim credits under Sections 45X, 45Y or 48E of the tax code.
The committee said the tax law signed that day “disqualifies tax credits for licensing agreements that are modified after the bill’s enactment.” It asked for a reply by February 4.
A Ford spokesperson said on Wednesday the company still expects to qualify for a federal battery manufacturing tax credit.
Fathom Due in 2027
The Fathom is the first model on the Universal EV Platform. Ford named the truck in August and set a starting price of $28,350, or $29,945 with destination, with a full reveal and pre-orders in early 2027 and deliveries in the fall. “The launch remains on track for fourth quarter next year,” Farley said in October.
The company plans to begin building prototypes with production-qualified parts in the first quarter of 2027. It said in October it had cast more than 5,000 aluminum unicastings for the truck.
The battery will also feed power back to a home. “AC bidirectional power lets a vehicle receive electricity from a properly equipped home and supply power back to it,” Poon wrote, a feature that requires Ford’s Home Power Station.
A Second Battery Business
Ford tied the milestone to its energy storage unit. “The knowledge we’re building in Michigan is already informing Ford Energy’s preparations for battery energy storage production in Glendale, Kentucky,” Poon wrote.
“Today represents more than the start of production in Marshall. It represents Ford officially becoming a battery manufacturer,” Dave Carroll, President of Ford Energy, wrote in a LinkedIn article on Wednesday. “And these batteries are shipping on time.”
Carroll, named to the role in August, said the unit’s production “is aligned to Investment Tax Credit requirements and domestic content standards.”
Ford Energy, launched on May 11, plans to deploy at least 20 gigawatt-hours a year of container-sized storage systems built around LFP prismatic cells, with first customer deliveries planned for late 2027. Ford has said it will invest roughly $2 billion in the business.
The Glendale plant came to Ford through its exit from the BlueOval SK venture, when it also assumed a $3.8 billion Department of Energy loan.
Both programs weigh on Ford’s EV unit. Model e lost $1.06 billion in the third quarter, and its forecast loss of about $4.0 billion for 2026 includes about $1 billion of additional investment in the Universal EV Platform and Ford Energy.